Snow Removal Update - Feb 6, 2025

Posted on
Expand Image
Crews are nearly finished Priority 3 routes and plan to move into residential clearing with Zone A on Friday. They'll be moving east to west this time around.

Attached is a map of the completed work in black, dark blue is windrowed for pickup tomorrow.

Roads completed today:

  • 10 Ave to 61 St to 11 Ave to 62A to 9 Ave
  • 54 St to 15 Ave to 55 St to 18 Ave to Edson Dr.
  • 10 Ave from 48 St to 56 St.
  • 52 St from 4 Ave to 10 Ave.

Work for tomorrow:

  • 8 Ave from 47 to 48 St to 9 Ave
  • 43 St from 4 Ave to 8 Ave
  • 50 St from 8 Ave to 12 Ave
  • Residential Zone A

Please watch for snow removal signs and move vehicles accordingly.

Please report any concerns to the Town by using our Report-a-Problem feature on our mobile app or website (https://www.edson.ca/services/report-a-problem).

We appreciate your cooperation as we work to keep our streets safe and passable.