Current Update

Snow Removal Update – February 20, 2025
We have completed Zone D and have started work in Zone E.
Attached is a map of the completed plowing work in Black. Windrows in Blue.
Roads completed today:
- 53 St to 11 Ave to 54 St
- 54th st from 13th Ave to 12th ave
- 14th ave to 54th st to 14a ave to 53rd st
- 15th ave from Edson Drive to 54th st
Windrowed for pick up tomorrow:
- 16th ave off 55th st
- 54th st from 15th ave to 18th ave
- 53rd st from 16th ave to 18th ave
- 52nd st from 16th ave to 18th ave
- 16th ave off Edson Drive to 53rd s
Work planned for Thursday – Residential E:
- 16th ave off 49th st
- 17th ave from 48th st to dead end
- 18th ave from 48th st to 49th st
- 50th st to cul de sac off 12th ave
Please move vehicles from Zone E streets to help crews work efficiently.