Snow Removal Update - Dec 20, 2024

Posted on
Residential and Priority 1-3 Routes Expand Image
Residential and Priority 1-3 Routes

December 20, 2024

As we head towards the holidays, we're making great progress with snow removal. A second crew has been activated, and we've restarted work on Priority 1, 2, and 3 routes.

Completed Work:

Priority 1 Routes:

  • 6 Ave from 40 St to 55 St
  • 42 St from 4 Ave to 6 Ave
  • 51 St from 1 Ave to Edson Dr to 48 St
  • 49 St from 1 Ave to 13 Ave
  • 48 St from 1 Ave to 9 Ave
  • 13 Ave from 48 St to 56 St

Residential Zones:

    • Finished Priority 4 Zone D
    • Nearly completed Zone C
    • Continued work on cul-de-sacs

Planned for Sunday, December 22:

  • Finish Zone C
  • Start Zone B
  • Continue Priority 1 routes
  • Keep working on cul-de-sacs

Thank you for your patience.

Please report any concerns to the Town by using our Report-a-Problem feature on our mobile app or website (https://www.edson.ca/services/report-a-problem).

www.edson.ca/snow for more information, including Priority Route Maps.