The Town of Edson is proceeding with the construction of the 10th Ave and 54th Street Sanitary upgrade. GS Holdings Company Ltd. O/A GS Construction has been contracted by the Town to complete this work.

Project Details:

  • Construction of the 54th Street sanitary upgrade will start at the intersection of 1st Ave and 54th Street on April 29, 2024, (weather permitting) and will proceed north along 54th Street as per the map below.
  • Construction for the 10th Ave sanitary upgrade is anticipated to commence on June 20th, 2024.
  • The project is expected to last approximately 90 working days, with completion targeted by mid-August 2024.
  • During construction, there will be temporary closures of certain intersections along 54th Street and 10th to through traffic.
  • The contractor, along with a representative from the engineering firm, will be in contact with each affected resident prior to construction to provide updates on affected services, including temporary water access, property access, parking, and garbage collection arrangement.